Events

27.10.2014

Inter RAO, GE and Rostec launched the new gas turbine facility in Russia

Russian Gas Turbines LLC — a joint venture between GE (NYSE: GE), Inter RAO Group, and United Engine Corporation (UEC, a subsidiary of state corporation Rostec) — has opened a new factory in the city of Rybinsk in Russia’s Yaroslavl Region to manufacture, sell, and service GE 6F.03 (6FA) gas turbines.
10.10.2014

Inter RAO - Engineering LLC has completed the delivery of main equipment to the construction site of the Power Generation Unit No.4 of the Permskaya SDPP

Inter RAO — Engineering LLC has completed the delivery of main equipment to the construction site of the PGU-800 combined cycle gas turbine of the power generation unit currently under construction at the Permskaya SDPP. A steam turbine, two gas turbines and three electric power generators have been delivered to the Thermal Power Plant site.
22.09.2014

First Shipment of Major Equipment is now on Site for Construction of 420 MW CCGT Unit No.12 at Verkhnetagilskaya SDPP

Inter RAO — Engineering LLC (100% subsidiary of Inter RAO Group) has signed a contract with Bangladesh Power Development Board for overhaul of Unit No. 5, 210 MW in capacity, of the Ghorashal Thermal Power Station in Bangladesh. The total value of the contract is USD 29.9 million.
09.09.2014

“Inter RAO – Engineering LLC” has signed a contract for overhaul of Unit No.5 of the Ghorashal TPS in Bangladesh

Inter RAO — Engineering LLC (100% subsidiary of Inter RAO Group) has signed a contract with Bangladesh Power Development Board for overhaul of Unit No. 5, 210 MW in capacity, of the Ghorashal Thermal Power Station in Bangladesh. The total value of the contract is USD 29.9 million.
20.08.2014

«Hot Setup» Began at Unit No. 2 of Yuzhnouralskaya TPP-2

The first fire of the Combined Cycle Plant (CCP) was performed at Unit No. 2 of Yuzhnouralskaya Thermal Power Plant-2 as part of testing and adjusting the combined cycle power equipment. This is a key commissioning milestone for the main equipment of the Unit.
05.08.2014

Commissioning Started at Unit No. 2 of Yuzhnouralskaya TPP-2

A gas and steam turbine of Unit No. 2 has been tested at low barring speed on the construction site of Yuzhnouralskaya Thermal Power Plant-2 (TPP-2). This is a major milestone in the power facility construction project that means transition from mechanical completion and pre-commissioning to commissioning. The “first fire” of the turbine and run-up to idling are expected on site in the coming days.
23.07.2014

Inter RAO - Engineering LLC will perform overhaul of Unit No.5 
Ghorasal TPP in Bangladesh

Inter RAO - Engineering LLC (100% subsidiary of Inter RAO Group) has won the tender for execution of works on overhaul of Unit No.5 with the capacity of 210 MW at Ghorasal TPP, Bangladesh. The company has been officially informed thereof by Bangladesh Power Development Board.
14.07.2014

Inter RAO - Engineering will perform design works for E.ON Russia

According to the results of open competitive bidding procedures, Inter RAO - Engineering will perform design and survey works within the framework of programs for technical retrofitting of Shaturskaya GRES and Surgutskaya GRES-2 being E.ON Russia’s branches. Teploenergoproekt, an Inter RAO
01.07.2014

Board of JSC Inter RAO approves new edition of corporate dividend policy and 2014-2016 cost management program

The Board of JSC Inter RAO approved the new edition of the Dividend Policy of JSC Inter RAO and consolidated cost management program at an absentee meeting on June 30, 2014.
05.02.2014

Inter RAO – Engineering Certified for Compliance with International Standards

LLC Inter RAO – Engineering received certificates of compliance confirming that its management systems meet the requirements of the following international standards: ISO 9001:2008 – Quality Management Systems, ISO 14001:2004 – Environmental Management Systems, and OHSAS 18001:2007 – Occupational Health and Safety Management Systems.
05.11.2013

Inter RAO Group Launches Dzhubginskaya TPP

Inter RAO Group successfully launched Dzhubginskaya thermal power plant (TPP) with combined installed capacity of 180 MW.
28.10.2013

Inter RAO Group Launches Power Generation Unit 4 at Gusinoozyorskaya Thermal Power Plant

Inter RAO Group successfully launched the 210 MW pulverized coal Power Generation Unit 4 at Gusinoozyorskaya thermal power plant (TPP), bringing the total installed capacity of the plant to 1,130 MW.
21.10.2013

New gas turbines safely arrived to the construction site of the new power generation unit of Permskaya TPP

A logistically challenging delivery of two Siemens SGT5-4000F gas turbines and two Siemens SGen5-1000A generators was successfully completed for the 800 MW Generation Unit 4 of Permskaya TPP currently in construction.
30.09.2013

Steam Turbine Delivered to Construction Site of the Second Power Generation Unit at Yuzhnouralskaya TPP-2

A unique delivery of SST-3000 steam turbine to construction site was successfully completed as a part of the second unit construction project at Yuzhnouralskaya TPP-2.
27.08.2013

Permanent Grid Connection of Yuzhnouralskaya TPP-2 Power Generation Unit

The first power generation unit of the new Yuzhnouralskaya TPP-2 currently under construction has been permanently connected to 220 kV switchgear.
26.03.2013

INTER RAO UES Group starts construction of unit 12 at Verkhnetagilskaya TPP

INTER RAO UES Group started the construction of a new 420 MW steam-gas power generation unit at Verkhnetagilskaya TPP.
05.03.2013

INTER RAO UES has begun the construction of the fourth power plant of the Perm GRES

The INTER RAO UES Group has started to build a combined heat and power plant on the Perm GRES with an established capacity of 800 MW.
20.02.2013

INTER RAO UES has increased the capacity of Tomsk thermal power STATION-1

Tomsk thermal power station-1, OJSC TGK-11 (a member of the INTER RAO UES Group) has commissioned a gas turbine plant (GTP) with an installed electric power capacity of 14.7 MW and thermal power capacity of 19.5 GCal/hr.
16.11.2012

INTER RAO UES launches new power generation unit at Kharanorskaya TPP

INTER RAO UES Group launched the new 225 MW Power Generation Unit 3 at Kharanorskaya TPP in Zabaykalsky Krai.
09.11.2012

INTER RAO UES Group launched a new 450 MW CCGT unit at Urengoyskaya TPP

The new 450 MW CCGT steam-gas unit increased the installed capacity of Urengoyskaya TPP from 24 MW to 474 MW.
31.10.2012

GE and joint venture partners celebrate groundbreaking for 6FA gas turbine facility

GE (NYSE: GE) and two Russian joint venture partners, INTER RAO UES and United Engine Corporation, today held a groundbreaking ceremony for the Russian Gas Turbines LLC Manufacturing Facility
15.10.2012

LLC INTER RAO Engineering and JSC Moldavskaya GRES signed a contract

LLC INTER RAO Engineering and JSC Moldavskaya GRES signed a contract for elaboration of pre-feasibility study for reconstruction of two power-generating units at Moldavskaya SDPP.
01.10.2012

Turbines are delivered to the “Olympic” Dzhubga TPP

Two gas turbine units of 180 MW (2X90) total capacity are delivered to the Dzhubga TPP (Krasnodar region) construction site.
17.08.2012

Operation center was held with respect to power units constructions at Cherepetskaya SDPP

The regular operation launch center on realization of the project “Construction of two power units with capacity of 225MW at the Cherepetskaya SDPP” under the leadership of LLC INTER RAO Engineering took place.
03.08.2012

The “hot” adjustment is in process at the Kharanorskaya SDPP

On the 3rd of August steam-water-oxygen boiler cleaning of power unit No.3 started at the Kharanorskaya SDPP.
30.07.2012

Main transformer assembly on the Gusinoozerskaya SDPP is completed

On the 30th of July of 2012 as a part of the project “Reconstruction and recovery of power unit No.4 on the Gusinoozerskaya SDPP” the main transformer mounting TDC-250000/220 produced by LLC Togliatti transformer was completed.
26.07.2012

The main fuel delivery machine is delivered to Cherepetskaya SDPP

On the 26th of July the rail-mounted coal stacker-reclaimer UZR-1200/600 was delivered to the construction of power units No.8 and No.9 of the Cherepetskaya SDPP, which is the main part of fuel delivery system of the power unit.
16.07.2012

Turbines are dispatched for Dzhubga TPP

On the 16th of July a vessel with two gas-turbine units manufactured by General Electric (GE) designed for Dzhubga TPP departed from port Houston (USA).